The Denver Basement Finishing Guide
Cost, code, permits, and city-by-city notes from a Denver-metro basement crew.
Most basements in the Denver metro are the cheapest square footage you’ll ever add to your house. The foundation is poured, the roof is on, the space is already heated a little. What you’re paying for is turning a concrete box into rooms people actually want to be in, and doing it in a way that passes inspection, stays dry, and still looks good in ten years.
We’re Gribbons Group, a basement finishing and remodeling crew working across the Denver metro. This guide is everything we walk homeowners through before they sign anything: what it costs and why, what code requires for a bedroom, how permits work in your city, and the mistakes we get called in to fix.
It’s long. Use the table of contents and jump around.
Watch: our 20-step basement process (4:37)
Want a number for your basement? See what it costs and what permits cost in your city, or call our 24/7 line at (720) 223-9003 (calls only).


Contents
- What it costs to finish a basement in Denver
- Layouts that work
- Bedrooms and egress windows
- Bathrooms and below-slab plumbing
- Permits and inspections
- How We Finish a Basement: Our 20-Step Process
- Radon
- Moisture, waterproofing, and Colorado’s swelling soils
- Ceilings, soffits, and headroom
- Heating and cooling the basement
- How long it takes
- Paying for it, and what it’s worth
- Mistakes to avoid
- City-by-city notes for the Denver metro
- FAQ
1. What it costs to finish a basement in Denver
Straight answer: most full basement finishes we do start around $60,000. A small open rec room can come in under that. A large basement with two bedrooms, a full bath, a wet bar, and nicer finishes can run well past $120,000.
Public Denver-area numbers land in the same place. Recent local cost guides put a Denver basement finish at roughly $45 to $105 per square foot, with a lot of projects in the $80–$95 range once a bedroom and bathroom are involved (Castle Builds, Aug 2026; Apollo Renovation). That’s a wide spread, and it should be. Two basements with the same square footage can be $40,000 apart.
What actually moves the price
Square footage matters, but it isn’t the biggest swing. These are:
- Bathrooms. The single biggest variable. If the builder left a rough-in (capped drain lines in the slab), a bathroom is straightforward. If not, we cut the slab, trench to the main sewer line, set new drains and vents, and re-pour. Sometimes the main line sits too high and you need an ejector pump. That can add thousands per bathroom.
- Egress windows. Every new bedroom needs one, and if you don’t already have a code-compliant window, that’s a concrete cut, a window, a well, a ladder, and drainage. Several thousand dollars each.
- Wet bars and kitchenettes. A sink and some cabinets is one price. A second kitchen with a range and full-height cabinets is another, and in some cities it triggers extra zoning questions.
- Finish level. LVP versus tile. Builder doors versus solid-core. Can lights versus a lighting plan. This is where premium and luxury jobs separate.
- House age. Older homes bring low ceilings, old electrical panels, cast-iron drains, and ductwork that hangs in the worst possible place. Newer homes usually have 8- or 9-foot basement walls and a rough-in already in place.
- What’s in the way. Beams, ducts, gas lines, the water heater, the furnace, the sump pit. Moving any of it costs money. Working around it costs design time.
Rough line items
These are typical ranges we see and that show up in public Denver guides. Your job might fall outside them.
| Item | Typical range | What drives it |
|---|---|---|
| Design, drawings, permits | $1,500–$4,000 | City, engineer letters, revisions |
| Framing (incl. soffits) | $7,000–$15,000 | Room count, soffits around ducts |
| Electrical | $5,000–$12,000 | Circuits, lighting plan, panel upgrade |
| Bathroom plumbing | $8,000–$20,000 | Rough-in or not |
| HVAC extension | $3,000–$9,000 | Supply and return runs, zoning |
| Egress window + well | $2,000–$5,000+ each | Foundation thickness, well size, grade |
| Radon system | $1,000–$2,500 | Sub-slab layout |
| Insulation + drywall | $8,000–$18,000 | Ceiling drywall vs. drop ceiling |
| Flooring | $4,000–$15,000 | LVP vs. carpet vs. tile |
| Trim, doors, paint | $5,000–$14,000 | Room count, door quality |
Source for line-item ranges: Castle Builds 2026 Denver guide; radon from CDPHE.
2. Layouts that work
The best basement layouts start with the stuff you can’t move: the stairs, the furnace and water heater, the main beam and posts, the sewer line, and the windows.
What usually works in Denver-metro houses:
- Bedrooms on the window walls. Bedrooms need egress. Put them where windows already are, or where the outside grade makes a new well easy. Don’t put the bedroom on the side with the driveway or the neighbor’s fence two feet away.
- Bathroom close to the main sewer line. The shorter the trench, the cheaper the bathroom. If you have a rough-in, the bathroom goes there unless there’s a very good reason.
- Big open room at the bottom of the stairs. That’s where people end up anyway. TV, sectional, maybe the bar along one wall.
- Keep a real mechanical/storage room. Don’t box the furnace into a closet you can’t work in. Code requires working clearance in front of fuel-burning appliances, and your HVAC tech will thank you.
- Bar on a plumbing wall. Put the wet bar back-to-back with the bathroom when you can, so they share drain and vent lines.
Popular layouts we build:
- Guest suite: bedroom, full bath, small living area. Great for visiting parents or a teenager who wants space.
- Entertainment level: big family room, wet bar, half bath, gym or office.
- Two bed, one bath “second floor”: for growing families who don’t want to move.
- Basement apartment: separate entrance, kitchenette, its own bath. This one has extra zoning and fire-separation rules, so read our basement apartment page first.
More layout ideas: basement finishing ideas and walkout basements.
3. Bedrooms and egress windows
A room with a closet isn’t automatically a bedroom. To be a legal sleeping room (and to count when you sell), it needs an emergency escape and rescue opening. Denver’s residential permitting checklist calls for “at least one emergency escape and rescue opening in the basement, habitable attic, and in every sleeping room,” with window sizes and well dimensions shown on the plans (Denver CPD residential permitting guide). Lakewood says the same thing: egress in every bedroom, and basements without bedrooms still need at least one egress window or exterior door (Lakewood basement finish handout).
Under the International Residential Code most metro cities adopt (with local amendments), the usual numbers are below. Your city’s adopted edition has the final say:
- Net clear opening of at least 5.7 sq ft (5.0 sq ft allowed for grade-floor openings)
- At least 24 inches clear height and 20 inches clear width
- Sill no more than 44 inches off the finished floor
- A window well at least 9 sq ft in area and 36 inches out from the wall, with a permanent ladder or steps once the well is deeper than 44 inches
Other bedroom basics inspectors check:
- Smoke alarms in each bedroom and outside sleeping areas, hardwired and interconnected where practical; CO alarms near sleeping rooms in homes with gas appliances or an attached garage (Lakewood requires them within 15 feet of sleeping rooms).
- Ceiling height. Lakewood requires a 7′-0″ minimum finished ceiling in habitable areas, with allowances in bathrooms. Beams and ducts can project lower under IRC rules, but check your city.
- Light and ventilation. Lakewood’s handout calls for glazing equal to at least 8% of the room’s floor area, with half of it operable, or approved alternatives.
Cutting a new egress opening in a foundation wall usually needs an engineer’s design. Lakewood says so explicitly; Golden flags egress windows as needing engineering too (Golden required permits guide). We handle that.
Deep dive: basement bedroom requirements in Colorado and egress windows.
4. Bathrooms and below-slab plumbing
Look for capped pipes sticking out of the slab, usually a 3″ drain, a 2″ drain, and a vent stubbed up the wall. That’s a rough-in. If you have one, you’re in good shape.
If you don’t:
- We locate the main sewer line and check its depth.
- If it’s deep enough, we saw-cut the slab, trench, set drains with the right slope, tie in vents, get the underground plumbing inspected, and re-pour.
- If the main line is too shallow (common in some older homes), the toilet and shower drain to an ejector pit that pumps waste up to the main line.
Other bathroom details that matter in a basement:
- Ventilation. A real exhaust fan ducted outside. Basement bathrooms with no window need it most.
- Shower ceiling height. Aurora’s basement guide notes a minimum 6’8″ over a 30″x30″ area at the showerhead (Aurora/ICC basement finish guide). Plan around ducts.
- Waterproof shower walls. Cement board or a membrane system, never drywall. Denver’s checklist requires nonabsorbent surfaces at tub and shower floors and walls.
- Sewer permits. In Denver, some projects also need a Sewer Use and Drainage Permit (SUDP) (Denver residential interior remodel).
More: adding a basement bathroom.
5. Permits and inspections
We handle permits across the Denver metro. Drawings, submittals, corrections, scheduling inspections, meeting inspectors. You don’t have to learn your city’s portal.
Every city on this page requires a permit to finish a basement. Denver’s rule of thumb: you need permits when you change the floor plan, add or move doors and windows, add egress, reroute ductwork, or add or move electrical or plumbing fixtures. That’s every real basement finish.
Typical inspection sequence (exact names vary by city):
- Underground plumbing (if the slab is cut)
- Rough framing, electrical, plumbing, mechanical
- Insulation
- Drywall (some cities)
- Final
Why permits matter beyond “it’s the law”: unpermitted square footage can cause problems with appraisals, insurance claims, and resale. Douglas County even publishes rough-inspection requirements for basements finished without a permit, which usually means opening walls back up (Douglas County basements & remodels).
More: basement permits in Denver.
6. How We Finish a Basement: Our 20-Step Process
Every basement is different, but the order of operations isn’t. This is the sequence we run on every job, and it’s the reason inspections pass the first time and nothing gets torn back open. To show what each step really looks like, we’ll follow one of our recent jobs: a recent basement we finished in Highlands Ranch.
Where the inspections fall. The rough inspections (framing, electrical, plumbing and mechanical) come after steps 5–8, once every trade is roughed in and before anything gets covered. Fire blocking and insulation get inspected after step 9, drywall after step 10 (Douglas County checks drywall before tape), and the final inspections come at the end, around steps 19–20. If we cut the slab for a bathroom drain, an underground plumbing inspection happens back in step 5, before the concrete gets patched.
Step 1: Planning, design and permitting
We measure the space, find the beams, ducts and drain lines, and draw a layout that works around them. Then we pull the permit and submit plans to the city or county, and nothing gets built until the plans are approved. On that job, we started from a drawing of the existing unfinished basement and got the Douglas County permit approved before work started.

Step 2: Egress door or window cuts
Any basement bedroom needs a code-compliant way out, usually an egress window with a window well. We cut the foundation, set the well and the window early, because it’s the messiest step and it changes how the framing gets laid out.

Step 3: Engineering or structural work
Some basements need an engineer before anything goes up: a new egress opening in the foundation, a beam or post that needs to move, or a cracked or heaving slab. We bring in the engineer, follow the letter, and turn it in with the permit so the inspector has it at rough. Douglas County wants engineer’s reports filed at least 24 hours before the rough inspection request.
Step 4: Framing
Walls go up, soffits get framed around ducts and beams, and doorways and closets take shape. On Front Range slabs, we float the walls that sit on concrete so a swelling slab can’t push up into the floor above. That job’s permit called for a 2″ float.


Step 5: Plumbing rough
The plumber runs supply and drain lines for the bathroom, bar or laundry, and sets the shower valve and the tub or shower pan. If the slab has to be cut to reach the drain, the underground plumbing gets inspected before we patch the concrete. On that job, the shower valve and the shower pan were set at rough.



Step 6: HVAC rough
We extend supply and return ducts so every room actually gets heated and cooled, not just the room by the furnace. A bedroom with no return is a cold room with the door shut. In Douglas County, the rough HVAC inspection is scheduled together with rough framing.

Step 7: Misc items (radon mitigation, whole-house vacuum, etc.)
Anything that runs inside the walls has to go in now: radon mitigation piping, central vacuum lines, low-voltage, speaker wire, data and security. Once the drywall’s up, adding these costs a lot more.
Step 8: Electrical rough
The electrician runs circuits, sets boxes for outlets, switches and lights, and adds the smoke and CO alarms code requires. After this step, the whole basement is ready for the rough inspections: framing, electrical, plumbing and mechanical.
Rough inspections happen here, after steps 5–8.
Step 9: Insulation, fire blocking, vapor barrier, draft stopping
We insulate the exterior walls and rim joists, fire-block the gaps between floors and around soffits, and seal drafts. Fire blocking slows a fire inside the walls, and insulation is what makes a basement feel like the rest of the house. Both get inspected before drywall.

Fire blocking and insulation inspections happen here.
Step 10: Drywall and backer board for tile and wet locations
Drywall goes on the walls and ceilings, and cement or foam backer board goes in the shower and other wet areas, where regular drywall would fail. Douglas County inspects drywall before tape, so we screw it off and wait for the inspector before we finish it.
Step 11: Water protection (waterproofing) and tile work
Before any tile goes on, we waterproof the shower: membrane on the walls, pan and niche. Tile isn’t waterproof; the membrane underneath is. Then the tile goes on. On that job, that meant white herringbone shower walls, a tiled niche and a tile floor.

Step 12: Millwork: doors, trim, cabinets, built-ins
Doors get hung, trim and casing go on, and vanities, bar cabinets and built-ins get set. This is when the space starts to look like finished rooms instead of a construction site.
Step 13: Flooring
Carpet, LVP or tile goes in after the messy work is done, so it doesn’t get beat up. In basements, we pick products that handle a concrete slab and the occasional bit of moisture.
Step 14: Electrical finish: lighting, switches, outlets
The electrician comes back to install fixtures, cover plates, switches, outlets and alarms, and tests every circuit. Recessed lighting gets aimed and dimmers set.
Step 15: Plumbing trim-out with fixtures and testing
The faucets, shower trim, toilet and sinks go on, then we run everything and check for leaks, pressure and drainage. We’d rather find a drip now than after you’ve moved furniture in.
Step 16: HVAC vents and calibration
Registers and grilles go on, and we balance the airflow so the basement doesn’t run 10 degrees colder than upstairs.

Step 17: Countertops
Vanity tops, bar tops or kitchenette counters get templated after the cabinets are set, then fabricated and installed.
Step 18: Appliances, custom glass, misc accessories
Appliances, the shower glass, mirrors, towel bars, closet systems and hardware go in last, because they’re easy to damage. On that job, the frameless glass shower enclosure was the finishing piece in the bathroom.

Step 19: Final touch-up
We walk every room with tape and fix nail pops, paint, caulk and anything that got dinged along the way. The final inspections (building, electrical, plumbing and mechanical) happen around this point.
Final inspections happen here.
Step 20: Thorough cleaning and customer delivery
We clean top to bottom, including the drywall dust in the ductwork, then walk you through the space: how things work, warranty information, and the permit closeout. You get the keys to a finished basement, not a punch list.




Want to see where your basement would land? Call our 24/7 line (720) 223-9003.
7. Radon
The Colorado Department of Public Health and Environment says about half of Colorado homes have radon above the EPA action level of 4.0 pCi/L (CDPHE, Jan 2026). Radon comes up through the soil, and the basement is where you’ll be breathing it.
What we tell every basement client:
- Test before you finish. CDPHE offers free test kits while supplies last.
- If it’s high, mitigate before the walls close. A sub-slab depressurization system is the standard fix. CDPHE says a Colorado mitigation system usually costs about $1,000–$2,000 unless the design is difficult (CDPHE testing and mitigation).
- Plan the pipe route. It’s much easier to run the vent pipe through a closet before drywall than to box it in after.
- Retest after the finish and every couple of years.
Some cities (Golden, for one) list radon mitigation systems as permitted work.
8. Moisture, waterproofing, and Colorado’s swelling soils
Finishing over a moisture problem is the most expensive mistake you can make. Before we frame anything, we look for efflorescence (white crust) on walls, staining, cracks, a wet sump pit, and how the yard drains.
The Front Range has its own issue: expansive clay soils. The Colorado Geological Survey calls swelling soil “Colorado’s most significant geologic hazard.” Some of these clays can expand up to 20% by volume when wet (Colorado Geological Survey). That’s why basement slabs here crack and heave, and why:
- Floating walls are required. Lakewood requires every wall built on a slab to be floated with at least 1½” of float and the drywall held at least 1″ off the slab. Most metro jurisdictions expect the same detail. The slab can move; the walls hang from the floor joists above.
- Grading and gutters come first. Water against the foundation feeds the clay. Fix downspouts and grade before you spend a dollar inside.
- Insulation details matter. Use a wall assembly that handles below-grade moisture, not fiberglass batts pressed against bare concrete with poly over the top.
More: basement moisture and waterproofing before finishing.
9. Ceilings, soffits, and headroom
Three ceiling options:
- Drywall. Cleanest look, best for resale. Plan access panels for shutoffs and cleanouts.
- Suspended (drop) ceiling. Cheaper and gives you access to everything above. Looks more “basement.”
- Exposed, painted. Industrial look, cheapest, loudest (sound travels).
Soffits are the boxed-in areas around ducts, beams, and pipes. Good soffit planning is the difference between a basement that feels like a real room and one that feels like a parking garage. We try to group ductwork into one clean run, line soffits up with walls, and keep them out of the middle of rooms.
Low ceiling? Read low-ceiling basement finishing. Lakewood, for example, requires 7′-0″ minimum in habitable spaces, and your plans have to show the height under beams and ducts.
10. Heating and cooling the basement
Basements stay cool in summer and can get cold in winter, especially on the north side. The usual approach:
- Extend supply and return runs into each finished room. Returns are the step people skip, and it’s why some basement rooms never get comfortable.
- Check whether your furnace has the capacity for the added space.
- Consider zoning or a separate mini-split if the basement fights the upstairs thermostat.
- Keep combustion air and clearances around the furnace and water heater. Aurora’s guide notes fuel-burning appliances can’t be in a bedroom or bathroom unless enclosed with outdoor combustion air and a self-closing door, and requires 30″ of working space in front.
Denver requires permits for new or rerouted ductwork.
11. How long it takes
Rough expectations for a typical full finish:
- Design and drawings: 1–3 weeks
- Permit review: varies a lot. Douglas County says 7–10 business days for typical processing; Wheat Ridge says 2–6 weeks. Denver depends on volume and whether you need a sewer permit too.
- Construction: about 6–10 weeks for most basements, longer with slab work, multiple egress cuts, or custom millwork.
Right now we’re finishing a basement in Golden: drywall is hung, the shower has cement board on the walls, and the wet bar’s half wall is framed. That job went from framing to drywall on schedule because the permit and egress work were sorted before the crew showed up.
Full breakdown: basement finishing timeline and our process.
12. Paying for it, and what it’s worth
How people typically pay: cash, a home equity line of credit (HELOC), a cash-out refinance, or a renovation loan. Talk to your lender about which makes sense with your rate.
What it’s worth: a finished basement adds usable living space, and a legal bedroom (with egress) is something buyers and appraisers notice. Be careful with any “you’ll get X% back” claims. Appraisers often value below-grade space differently from above-grade space, and return depends on your neighborhood. The surest value comes from doing it permitted, dry, and with legal bedrooms.
13. Mistakes to avoid
- Skipping the permit. It comes back at sale time, or after an insurance claim.
- Finishing over a moisture problem. Fix grading, gutters, and cracks first.
- Not testing for radon. Half of Colorado homes are high, per CDPHE.
- Calling it a bedroom without egress. It isn’t one, legally.
- Walls nailed tight to the slab. On Front Range clay, that’s how you get cracked drywall and stuck doors.
- No return air. The room is always cold or stuffy.
- Boxing in shutoffs and cleanouts. Leave access.
- Bathroom in the wrong spot. Put it near the sewer line.
- Choosing a contractor by the lowest bid. Compare scopes, not totals. Does it include egress, permits, radon, HVAC returns, and floating walls?
- Carpet in a basement bathroom or by the bar. Use LVP or tile.
14. City-by-city notes for the Denver metro
Code is similar across the metro, but who you file with, how you file, and what they ask for are not. Here’s what’s different in each place. Always confirm your address is inside city limits; unincorporated areas go to the county.
Denver
- Permit office: Denver Community Planning and Development (CPD), applications through Denver’s e-permits system.
- What’s different: Denver may require a Sewer Use and Drainage Permit (SUDP) alongside building and zoning permits; uploading everything at once lets reviewers run them at the same time. Denver’s checklist asks you to label a second kitchen or bar as a full or partial kitchen. Anything with a range, a 220-volt outlet, or a gas line counts as a full kitchen, which matters for zoning. Interior remodels over 2,500 sq ft of modified floor area fall under the city’s construction waste recycling rules (URCO).
- Homeowner permits: Denver lets owner-occupants pull their own permits only for single-family homes, with trade exams for electrical, plumbing, and mechanical work, and a one-year occupancy requirement.
- Sources: Residential Interior Remodel, Homeowner Permits
- Our page: Basement finishing in Denver
Golden
- Permit office: City of Golden Building Division, (303) 384-8151, 911 10th Street; online portal.
- What’s different: Golden lists basement finishes as requiring plan review. Every contractor on a permitted job must hold a Golden contractor license, and all licensed contractors must be on the permit before it’s issued. Golden building permits cover all trades in one permit. Golden flags new egress windows as needing engineering. The city also asks you to check the Wildland Urban Interface (WUI) map for your property, and to confirm your address is in city limits (unincorporated areas go to Jefferson County).
- What we’re doing there now: a full basement finish with a bathroom and wet bar is in progress in Golden.
- Sources: Building Permit Process, Required Permits Guide
Lakewood
- Permit office: City of Lakewood Public Works, permits through eTRAKiT.
- What’s different: Lakewood’s basement handout is one of the most specific in the metro. Plans must include a floor-to-ceiling section showing floating walls and the finished ceiling height in every room, including under beams and ducts. Walls on slab need at least 1½” of float. Minimum 7′-0″ ceilings in habitable space. Anyone hired must be registered with Lakewood, and electrical/plumbing contractors must also be state-licensed.
- Source: Lakewood Residential Basement Finish handout
- Our page: Basement finishing in Lakewood
Arvada
- Permit office: City of Arvada Building, online portal.
- What’s different: Arvada’s basement finish permit includes mechanical, plumbing, electrical, and egress windows, so no separate trade permits. Contractors need a Class B or Class C general contractor license with Arvada, and subcontractors sign on with Arvada’s Subcontractor Form. Owners who don’t live in the house must hire a contractor or get licensed.
- Source: Arvada Residential Interior
- Our page: Basement finishing in Arvada
Aurora
- Permit office: City of Aurora Building Division, 15151 E. Alameda Pkwy, (303) 739-7420.
- What’s different: Aurora’s basement guide asks for window sizes and well dimensions including the ladder, any changes to posts, beams, or joists, and any ceiling below 7 feet. Aurora also notes its inspectors offer free project consultations on what they look for. Aurora spans three counties (Arapahoe, Adams, Douglas), but the city handles the permit.
- Sources: Aurora DIY handbook
- Our page: Basement finishing in Aurora
Centennial
- Permit office: City of Centennial Building Division; apply online.
- What’s different: Centennial publishes its own single-family basement finish handout covering egress windows and wells, smoke detectors, ceiling height, insulation, fireblocking, light, and ventilation, and wants a basement floor plan with the application. Centennial runs its own building department even though it sits in Arapahoe County.
- Sources: Centennial basement finish handout, Apply for a Building Permit
- Our page: Basement finishing in Centennial
Littleton
- Permit office: City of Littleton Building & Development, electronic submittals.
- What’s different: Littleton wants existing and proposed plans, beam and ductwork details for basements, and plans from a structural engineer when the foundation or structure changes (like an egress cut).
- Source: Littleton residential submittal requirements
- Our page: Basement finishing in Littleton
Highlands Ranch
- Permit office: Highlands Ranch isn’t a city, so permits go through the Douglas County Building Division.
- What’s different: Douglas County requires a permit whenever walls are built or electrical is added, requires contractors to be registered and listed on the application, and quotes about 7–10 business days for typical processing. Plans must show unfinished areas as well as finished rooms. The county also publishes rough-inspection requirements for basements finished without a permit.
- Source: Douglas County Basements & Remodels
- Our page: Basement finishing in Highlands Ranch
Parker
- Permit office: Town of Parker Building.
- What’s different: Parker publishes its own Basement Finish Building Guide and accepts two paper sets or one electronic set, with a scaled plan showing rooms, fixtures, alarms, windows, structural changes, and ceiling heights.
- Sources: Parker Basement Finish guide, Forms and Regulations
- Our page: Basement finishing in Parker
Castle Rock
- Permit office: Town of Castle Rock Building Division, (720) 733-3527, permits through eTRAKiT.
- What’s different: Castle Rock has its own Basement Finish Checklist and Building Guide, wants plans as PDFs, and requires a Homeowner Affidavit if the owner does the work.
- Sources: Castle Rock residential permits, Basement Finish Checklist
- Our page: Basement finishing in Castle Rock
Westminster
- Permit office: City of Westminster Building Division; apply online under Residential Interior → Basement Finish.
- What’s different: Westminster wants framing plans when structure changes, electrical plans, and gas/fireplace details where they apply. Approved plans must be on site for inspections. Westminster also notes fire sprinkler work may need separate Fire Department approval.
- Sources: Westminster residential permit requirements, Resources
- Our page: Basement finishing in Westminster
Thornton
- Permit office: City of Thornton, permits through the city’s online application portal.
- What’s different: Thornton publishes a list of projects that require a building permit, and basement finishes are on it.
- Sources: Thornton permit portal, Projects requiring a permit
- Our page: Basement finishing in Thornton
Broomfield
- Permit office: City and County of Broomfield Building.
- What’s different: Broomfield uses a Basement Finish/Home Remodel Questionnaire with the plans (current form references the 2024 IRC and 2023 NEC) and requires an engineer-stamped report for interior structural changes. Inspections include combined rough electrical, framing, plumbing/mechanical, then insulation, drywall, and final.
- Sources: Broomfield basement finish handout, Broomfield FAQ
Wheat Ridge
- Permit office: City of Wheat Ridge Building Division, submittals through OpenGov.
- What’s different: Wheat Ridge lists basement finishes as permit-required and says review typically takes 2–6 weeks. Plan for that in your schedule.
- Source: Wheat Ridge Building Permits
Englewood
- Permit office: City of Englewood Building Division, online submittal.
- What’s different: Englewood’s “To Permit or Not To Permit” page spells it out: new drywall, wall changes, electrical, plumbing, and HVAC all need permits.
- Sources: To Permit or Not To Permit, Plan submittal requirements
Evergreen (and Ken Caryl)
- Permit office: Both are unincorporated Jefferson County, so permits go through Jeffco Building Safety, (303) 271-8260.
- What’s different: In Evergreen this is the big one. Adding a bedroom also triggers Planning & Zoning review and has to fit your septic system’s bedroom limit. Many mountain homes are on septic, so a basement bedroom isn’t automatic. Structural plans are required if walls, openings, beams, or stairs change. Mountain access and delivery also add cost and time.
- Sources: Jeffco Inside the Home, Jeffco Residential Interior Remodel Submittal Guide
- Our pages: Evergreen, Ken Caryl
Don’t see your city? We work across the Denver metro. Call our 24/7 line at (720) 223-9003.
15. FAQ
How much does it cost to finish a basement in Denver?
Most full basement finishes we do start around $60,000. Public Denver guides put it at roughly $45–$105 per square foot. Bathrooms, egress windows, and finish level move it the most.
Do I need a permit to finish my basement?
Yes, in every city on this page. We handle permits across the Denver metro.
Can a basement bedroom be legal without a window?
No. Every sleeping room needs an emergency escape opening: an egress window or an exterior door.
How long does a basement finish take?
Plan on design and permit time up front, then about 6–10 weeks of construction for a typical finish.
Should I test for radon before finishing?
Yes. CDPHE says about half of Colorado homes are above the EPA action level. Mitigation is easiest before the walls go up.
What’s a floating wall?
A wall that hangs from the floor framing above with a gap at the bottom, so the slab can move on expansive soil without cracking your drywall. Lakewood requires at least 1½” of float.
Can I add a bathroom without a rough-in?
Yes. We cut the slab and tie into the sewer line, or use an ejector pump if the line is too shallow. It costs more than using an existing rough-in.
Can I rent out my basement?
Maybe. Basement apartments have extra zoning and fire-separation rules that vary by city. See our basement apartment page.
Ready to talk about your basement?
Tell us what you want the space to do. We’ll walk it, flag the stuff that affects price (moisture, ceiling height, ducts, the sewer line), and give you a written quote.
Call our 24/7 line at (720) 223-9003. It’s answered around the clock.
Last reviewed October 2026. Code requirements change; your city’s adopted code and your permit reviewer have the final say.