Basement Stairs: Code Requirements in Colorado

The stairs are the main way in and out of your basement, and they’re one of the things a building inspector looks at when you finish it. Most of the time the existing stairs are fine. But a basement finish changes things around them: a new soffit over the stairwell, new flooring at the bottom step, a wall that comes down to open the stair up, or a storage closet built underneath. Each of those has a code rule attached.

Gribbons Group Corp finishes basements across the Denver metro. This page covers the stair rules most Front Range building departments use, what a finish tends to change, and what inspectors check. For the whole project, see our basement finishing guide.

Call 24/7 at (720) 223-9003. Calls only, answered by our AI assistant.

The short version

Denver-area cities and counties use the International Residential Code with their own amendments. Some are on the 2021 edition (stairs are section R311.7). Broomfield, Douglas County and Jefferson County are on the 2024 edition, which moved the same rules to R318.7. The core numbers didn’t change.

ItemRequirement
WidthAt least 36 inches clear above the handrail; at least 31-1/2 inches at the handrail with one rail, 27 inches with rails on both sides
HeadroomAt least 6’8″, measured straight up from the line connecting the tread nosings
Riser height7-3/4 inches max
Tread depth10 inches min
ConsistencyTallest riser no more than 3/8 inch taller than the shortest in a flight; same 3/8-inch rule for treads
Nosing3/4 to 1-1/4 inch projection, unless the tread is at least 11 inches deep
LandingsA floor or landing at the top and bottom, at least as wide as the stair and 36 inches deep on a straight run
HandrailRequired on at least one side when the flight has 4 or more risers; 34 to 38 inches high; continuous for the full flight
GuardsRequired on open sides more than 30 inches above the floor below; at least 34 inches high along the stair, 36 inches at landings and floors
LightingA light that covers the treads and landings, with a switch at each floor level when there are 6 or more risers

Douglas County’s basement finish guide restates these for basements, including the 6’8″ head clearance measured to the finished ceiling and a switch at the top and bottom of the stair.

Diagram of basement stair dimensions: 6 feet 8 inches minimum headroom measured straight up from the nosing line, 7-3/4 inch maximum riser height, 10 inch minimum tread depth, handrail 34 to 38 inches high, and nosing 3/4 to 1-1/4 inches. Not to scale.
Diagram: basement stair dimensions from the IRC figures on this page. Not to scale.

What a basement finish changes about your stairs

Finished basement in Highlands Ranch by Gribbons Group Corp, looking toward the basement stairs and the soffit over the stairwell.
A finished Gribbons Group Corp basement in Highlands Ranch, with the stairs and the soffit over the stairwell.

Headroom under new soffits and ducts

Ductwork, a beam or a plumbing line often runs right across the stairwell. Leaving it exposed in an unfinished basement is one thing. Boxing it in with a soffit drops the ceiling a few more inches, and the 6’8″ headroom is measured from the line of the nosings to whatever is lowest. We measure that before we design the soffit. Sometimes the fix is rerouting a duct, not boxing it. See low-ceiling basements and basement ceiling options.

The bottom step after new flooring

New flooring at the bottom of the stairs makes the bottom step shorter. Add an inch of subfloor and flooring and the bottom riser is now an inch shorter than the rest, and the code only allows 3/8 inch of difference. Broomfield’s handout says it directly: changing floor finishes on the stairs or landings can’t create a riser violation. We plan the floor build-up with the stair in mind. See basement flooring over concrete.

Diagram showing how one inch of new subfloor and flooring at the bottom of basement stairs shortens the bottom riser, and that the code allows only 3/8 inch of difference between the tallest and shortest riser in a flight. Not to scale.
Diagram: new flooring at the bottom shortens the bottom riser. The code allows only 3/8 inch of difference. Not to scale.

Opening up a closed stairwell

Many basement stairs run between two walls. Take one wall down to open the stair to the family room and that side becomes an open side, which brings in the guard rules:

  • A guard wherever the drop to the floor below is more than 30 inches.
  • At least 34 inches high along the stair (measured from the nosings) and 36 inches at landings and floors.
  • Openings small enough that a 4-3/8-inch sphere can’t pass through along the stair, and 4 inches at other guards. The triangle under the bottom rail at each step can’t pass a 6-inch sphere.

The handrail still has to be graspable, so a wide flat cap on a half wall usually isn’t enough on its own.

Handrails

Required on at least one side once the stair has four or more risers, which every full basement flight does. The details inspectors check:

  • 34 to 38 inches above the nosings.
  • Continuous from above the top riser to above the bottom riser, with the ends returned to the wall or ending at a post.
  • At least 1-1/2 inches of space between the rail and the wall.
  • A graspable shape. For a round rail, 1-1/4 to 2 inches across.

Light and switches

Six risers at 7-3/4 inches is 46-1/2 inches of rise. A finished basement’s ceiling alone has to be at least 7 feet in living space, so a basement stair is always taller than that. In practice a basement stair needs a light that covers the treads and landings and a switch at the top and the bottom, unless the light is on an automatic or remote control. The code sets the minimum at 1 footcandle at the center of the treads and landings.

Storage under the stairs

If you close in the space under the stairs and get into it through a door or an access panel, the walls, the underside of the stairs, and any soffits inside that space need 1/2-inch drywall on the enclosed side. Thornton’s basement guide notes this doesn’t apply when the space under the stairs is open to a larger storage or mechanical room. Jefferson County checks it at the drywall screw inspection.

The stair stringers also need fireblocking where the concealed spaces between them meet the top and bottom of the run.

Glass near the stairs

Broomfield’s handout lists glass in a stairway enclosure or within 60 inches of stairs or landings as a place that may need safety glazing. If your plans include a glass railing, a glass door at the bottom of the stairs, or a window near a landing, we check it on the drawings.

A door at the top of the stairs

The code requires a landing at the top and bottom of every stair, with one exception: an interior stair doesn’t need a landing at the top as long as the door doesn’t swing over the stairs. An older basement door that swings out over the top step is a problem we flag on the walkthrough.

Older homes and existing stairs

Not every older basement stair has to be rebuilt to today’s numbers when you finish the basement. How a city treats an existing stair you aren’t changing varies:

  • Broomfield writes it into its handout. For existing stairs in homes built before December 2003, the maximum riser is 8 inches and the minimum tread is 9 inches, instead of 7-3/4 and 10.
  • Other building departments decide based on the scope of work. If the stair is being rebuilt, moved, or widened, expect the new-construction numbers.
  • Denver classifies relocating stairs as structural work that isn’t “minor,” which puts the project in its Intermediate Residential review track. See our basement timeline for what that means for the schedule.

We look at the stairs on the first visit and tell you what the building department is likely to say before you see a drawing.

What inspectors check, and when

Jefferson County’s inspection guide lays out a typical order, and most metro building departments follow something close to it:

  1. Framing. All wall and structural framing, before anything is covered. On a basement job that includes soffits over the stairwell and any new guard or half-wall framing.
  2. Drywall screw inspection. Fastening, plus the 1/2-inch drywall in an enclosed under-stair space.
  3. Final. Handrails, guards, and safety glass in the required locations, along with the rest of the basement.

What does stair work cost?

Most full basement finishes we do, with a bedroom and a bathroom, land around $60,000 and up. Smaller projects start at our $22,500 minimum, and your written quote shows where every dollar goes.

Stair work isn’t its own line in our basement cost calculator, because it ranges from adding a handrail and a light switch to rebuilding a flight. We measure the stairs on the walkthrough and price whatever they need as its own line in your written estimate.

Licensed & Insured

Gribbons Group Corp holds these contractor licenses: Douglas County #A260170, Jefferson County Class B #1028872, City of Littleton #AEC002126, and City of Arvada #AEC13870. Electrical, plumbing, gas, and HVAC work is done by licensed subcontractors, and we schedule and coordinate their inspections.

Where We Work

We work across the Denver metro, including Denver, Aurora, Centennial, Lakewood, Littleton, Arvada, Golden, Highlands Ranch, Parker, Castle Rock, Ken Caryl, Evergreen, Westminster, Thornton, Broomfield, Erie and Brighton. We handle the permits and inspections for your project, from the application through final sign-off.

Related: basement finishing, basement layout ideas, egress windows, basement permits, and floating walls and framing.

Basement Stair FAQs

What are the code requirements for basement stairs?
Under the IRC used across the Denver metro: at least 36 inches wide, 6’8″ of headroom, risers no taller than 7-3/4 inches, treads at least 10 inches deep, no more than 3/8 inch of variation, a handrail on one side once there are four risers, guards on open sides more than 30 inches up, and a light with switches at the top and bottom.

Do basement stairs need a handrail?
Yes, on at least one side when the flight has four or more risers. It has to be 34 to 38 inches above the nosings and run the full length of the flight.

How much headroom do basement stairs need?
6’8″, measured straight up from the line connecting the front edges of the treads. A new soffit over the stairwell is the usual way people lose it.

Do I need a permit to replace basement stairs?
Yes. Stairs are structural. In Denver, relocating stairs puts the project in the Intermediate Residential review track. If the stair work is part of a basement finish, it goes on the same permit and plans.

Can I build storage under my basement stairs?
Yes. If it’s closed in with a door or access panel, the inside walls, the underside of the stairs and any soffits get 1/2-inch drywall.

Can basement stairs have open risers?
Yes, but where the stair is more than 30 inches above the floor below, the gap between treads can’t let a 4-inch sphere through.

Does new flooring affect my stairs?
It can. Flooring added at the bottom makes the bottom riser shorter than the rest, and the code allows only 3/8 inch of difference. Plan the floor height and the stairs together.

Request a Free Basement Estimate

Tell us what you want in your basement and send a photo of the stairs. We’ll measure them on the walkthrough and include anything they need in your written scope.